The City routinely evaluates road condition and maintains a priority based resurfacing program.
Streets remain open during resurfacing work; however, please makes sure vehicles are not parked in the roadway. If you have a sprinkler system, please ensure that the system is not spraying water into the road. Expect minor delays accessing your street while crews are working.
The work is done in phases:
Road | From | To | Start Milling | Start Paving | ||
N RIVER PKWY | ROSWELL RD | CARROLL MANOR DR (2nd) | Complete | Complete | ||
HUNTCLIFF TRCE | WEDGEWAY | RIVER RUN (2nd) | Complete | Complete | ||
GOLD CREEK CT | GROGANS FERRY RD | CUL-DE-SAC | Complete | Complete | ||
GRANTLEY CT | GROGANS FERRY RD | CUL-DE-SAC | Complete | Complete | ||
TROWBRIDGE RD | FIELDSBORN WAY | ROSWELL ROAD R/W | Complete | April 18, 2023 | ||
NORTHGREEN DR | SPALDING DR | NORTHGREEN DR | Complete | April 18, 2023 | ||
GLENLAKE PKWY | GLENRIDGE DR | FIFTY GLENLAKE PKWY | Complete | April 19, 2023 | ||
SPALDING DR | ROSWELL RD | SPALDING CT | April 17, 2023 | April 20, 2023 | ||
GLENCOURTNEY DR | W SPALDING DR | SELKIRK DR | April 18, 2023 | April 21, 2023 | ||
HIDDEN FALLS LN | SEVILLE CHASE | CUL-DE-SAC | April 19, 2023 | April 24, 2023 | ||
SUNNY BROOK LN | ROSWELL RD | BROOK DR | April 21, 2023 | April 26, 2023 | ||
SUNNY BROOK PL | SUNNY BROOK LN | EOP | April 21, 2023 | April 26, 2023 | ||
GREYFIELD PL | LONG ISLAND DR | GREYFIELD PL | April 28, 2023 | May 3, 2023 | ||
LONG GROVE CT | LONG GROVE DR | CUL-DE-SAC | April 28, 2023 | May 4, 2023 | ||
LONG GROVE DR | CUL-DE-SAC | CUL-DE-SAC | April 28, 2023 | May 4, 2023 | ||
LIMESTONE WAY | LONG ISLAND DR | LONG GROVE DR | April 28, 2023 | May 4, 2023 | ||