The City routinely evaluates road condition and maintains a priority based resurfacing program.

Streets remain open during resurfacing work; however, please makes sure vehicles are not parked in the roadway. If you have a sprinkler system, please ensure that the system is not spraying water into the road. Expect minor delays accessing your street while crews are working.

The work is done in phases:

  • Phase 1: Notice - Our goal is to provide at least one week's notice. The schedule takes into account weather and time to complete the roads in progress.
  • Phase 2: Milling - Crews mill (grind up) the old asphalt. Following the mill process, it can take up to 7 days before paving takes place.
  • Phase 3: Paving
  • Phase 4: Clean Up - Public Works crews inspect the quality of the paving work and the clean up the area as needed. If additional work is required, it is scheduled and typically completed within three business days.

Paving Schedule

       
 RoadFromToStart MillingStart Paving 
 N RIVER PKWYROSWELL RDCARROLL MANOR DR (2nd)CompleteComplete 
 HUNTCLIFF TRCEWEDGEWAYRIVER RUN (2nd)CompleteComplete 
 GOLD CREEK CTGROGANS FERRY RDCUL-DE-SACCompleteComplete 
 GRANTLEY CTGROGANS FERRY RDCUL-DE-SACCompleteComplete 
 TROWBRIDGE RDFIELDSBORN WAYROSWELL ROAD R/WCompleteApril 18, 2023 
 NORTHGREEN DRSPALDING DRNORTHGREEN DRCompleteApril 18, 2023 
 GLENLAKE PKWYGLENRIDGE DRFIFTY GLENLAKE PKWYCompleteApril 19, 2023 
 SPALDING DRROSWELL RDSPALDING CTApril 17, 2023April 20, 2023 
 GLENCOURTNEY DRW SPALDING DRSELKIRK DRApril 18, 2023April 21, 2023 
 HIDDEN FALLS LNSEVILLE CHASECUL-DE-SACApril 19, 2023April 24, 2023 
 SUNNY BROOK LNROSWELL RDBROOK DRApril 21, 2023April 26, 2023 
 SUNNY BROOK PLSUNNY BROOK LNEOPApril 21, 2023April 26, 2023 
 GREYFIELD PLLONG ISLAND DRGREYFIELD PLApril 28, 2023May 3, 2023 
 LONG GROVE CTLONG GROVE DRCUL-DE-SACApril 28, 2023May 4, 2023 
 LONG GROVE DRCUL-DE-SACCUL-DE-SACApril 28, 2023May 4, 2023 
 LIMESTONE WAYLONG ISLAND DRLONG GROVE DRApril 28, 2023May 4, 2023