Tier One
Roswell Road at Morgan Falls Road Intersection Improvement ($6,100,000) - safety and traffic operational improvements at this intersection.
- Hammond Drive Corridor Improvements ($44,600,000) - Phase two of the Hammond Dr. Corridor Improvements. This phase will improve safety, mobility and pedestrian/bicycle access along Hammond Dr. from Roswell Rd. to Boylston Dr. and Barfield Rd. to Glenridge Dr.
- Northside Drive at 1-285 Concept Development ($1,100,000) - developing a concept that will improve safety, mobility and pedestrian/bicycle access along Northside Dr. between Interstate North Parkway and New Northside Dr.
- Capital Sidewalk Program ($16,000,000) - Improving pedestrian access and safety by completing sidewalks throughout Sandy Springs.
- Riverside Drive at Heards Ferry Road Corridor Improvements - Design ($1,500,000) - Designing to improve safety, operations and mobility along Riverside Dr. from I-285 to River Valley Dr.
- Roswell Road Safety Project Concept Development and Design ($4,000,000) - Designing to improve safety and operational improvements on Roswell Rd. from Carpenter Dr. to Hammond Dr.
- Mid-Block Crossing Program ($4,000,000) - Designing and constructing safe pedestrian access at key mid-block locations to improve safety and connectivity.
- Bridge Program ($5,000,000) - Improves and replaces existing bridges throughout Sandy Springs.
- Peachtree Dunwoody at Johnson Ferry Road Intersection Improvements - Construction ($3,589,697) - Constructing safety and operational improvements at the intersection of Peachtree Dunwoody Rd. and Johnson Ferry Rd.
- Peachtree Dunwoody Road Corridor Improvements - Concept Development ($2,000,000) - developing a concept to improve safety, mobility and pedestrian/bicycle access along Peachtree Dunwoody Rd. from Mount Vernon Hwy. to Spalding Dr.
- Holcomb Bridge Road Multi-Use Path ($4,300,000) - Constructing a multi-use side path along the west side of Holcomb Bridge Rd.
- Glenridge Connector at Johnson Ferry Road Intersection Improvements ($3,300,000) - Designing the intersection improvements to increase safety and operations and purchasing right-of-way for this project.
Tier Total: $95,489,697
Tier Two
- Glenridge Connector at Johnson Ferry Road Intersection Improvements ($3,951,123) - constructing the intersection improvements that were designed in Tier I.
- Intelligent Transportation System (ITS) Program ($4,300,000)
- Intersection Program ($4,300,000)
- Capital Sidewalk Program ($4,300,000)
Tier Total: $16,851,123
Tier Three
- Access Management Program ($16,851,122)
Total of All Tiers: $129,191,942