Park Projects

Abernathy Greenway South Trail Park

Project Description: 

The Abernathy Greenway South Trail Park includes a slate chip walking trail, landscaping, park benches, bike racks, pet waste stations and trash cans along the designated areas.

Site One: Southside of Abernathy Road between Roswell Road and Johnson Ferry Road

Site Two: Northeast Parcel at the intersection of Abernathy Road and Wright Road

Project Timeline/Status

Construction is estimated to begin by Fall 2017 with completion by Spring 2018, weather permitting. 

Status-October 2017: 

Construction is underway at the Northeast Parcel. The concrete path was recently completed and turf is scheduled to be installed by late October. Construction on site one will start after construction on the Northeast Parcel (site two) is finished. 

Project Rendering:

Abernathy Southside Rendering