Project Status: Under Construction

Project Description: Brandon Mill Road Sidewalk (West Spalding to Marsh Creek Crossing)  

Brandon Mill Road Sidewalk layout

Fall 2018: Construction completed 

May 2018 Update: Construction substantially completed-punch list items remain.  

December 2017 Update

In November, The City negotiated a legal agreement with the previous contracting firm and its bonding company. We are currently working with our new contractor in finalizing plans to complete the sidewalk and associated infrastructure, including the retaining wall.  You should expect to see construction resuming by the first of the year. The estimated time for completion is 90 days following construction start.

 