Project Status-November 2018: Construction is underway. The curb and gutter work at the north end of Dudley and the City Atlanta has been completed.  

  • The project construction sequence will be as follows:
    1. North end (4797 Dudley Ln, 4811 Dudley Ln, 4825 Dudley Ln, 4805 Powers Ferry Rd, 4831 Powers Ferry Rd) curb and gutter, sidewalk, and driveways.  The City will also be repaving this section to allow water to adequately flow down Dudley Lane to a storm sewer inlet located on Powers Ferry Road.
    2. City of Atlanta curb and gutter and sidewalk
    3. South end and progress back to north end of the project (curb and gutter, sidewalk, walls, and driveways).

Construction is expected to be completed by late 2018/early 2019, weather permitting. 

Please direct any questions to the City’s Project Superintendent, John Benson, at 678-206-4392.  You may also contact the City's Citizen Response Center @ 770-730-5600. 